Tempe's ADU rules read a lot like Phoenix's on the pipes and wires, with two things layered on top: every casita must have its own address, and the City charges a water development fee whenever a project creates an additional dwelling unit, meter or no meter. Here is how each connection works on a Tempe lot, what we verify, and what it costs.

The short version

In Tempe, your ADU shares the sewer and water service your home already has, gets its own SRP or APS electric meter as our standard, and gets its own address because the City requires one for every ADU.

Sewer
Tie into your home's existing sewer line. A separate tap to the main is a case-by-case City determination, not the default.
Water
Tie into your home's water line, after the meter. One meter per lot unless the Community Development Director approves a second.
Electric
New, separate SRP or APS meter for the ADU. The City defers to the utility on metering and requires a unique address for the unit either way.

Tempe lots are older and tighter than most of the East Valley, which usually means shorter trench runs but more mature landscaping, hardscape, and older sewer pipe in the way. Distance is still the biggest driver of cost; existing conditions are a close second here.

Sewer: share the lateral

Tempe's zoning code requires residential sewer, water, and utility connections to the ADU "in conformance with City standards" (Tempe Zoning and Development Code 3-402). Your ADU connects to your home's existing sewer line on private property. The City's sewer code lets the City Manager decide whether a separate building needs its own tap to the main, but on a normal residential lot the shared lateral is the expected path, and we confirm it with the Permit Center at plan review. Sewer is billed on your water account, so there's no separate sewer account for the unit.

What we verify at the site visit:

Water: one meter, and a development fee to plan for

Your ADU tees off your home's water line after the existing City meter, with its own shutoff valve. Tempe's water code says multiple meters serving a single service aren't permitted unless the Community Development Director approves, so one meter per lot is the default. The City has told Council its existing infrastructure can handle ADU demand, and meter sizing is settled at plan review under the plumbing code.

Electric: its own meter, and its own address regardless

Tempe's ADU FAQ answers the separate-meter question with "refer to your utility provider's requirements," so the City neither requires nor blocks a second meter. SRP serves most of Tempe and APS serves a portion; either will set a second residential meter once the City has permitted the unit. A separate meter is our standard because it gives the casita its own bill and adds no load to your home's panel.

Option: power from your home's panel

We can instead feed the ADU from your home's electrical panel, with one shared bill, when a load calculation shows your panel has room, usually a 200-amp service. It's often a fit for family or guest use, and if you have rooftop solar it's usually the better economics. Many older Tempe homes are on 100-amp or 125-amp service, in which case a new ADU meter is usually better value than upgrading the house.

What it costs in Tempe

Utility connections are priced per linear foot of trench plus fixed connection items. Your proposal shows the measured run lengths for your site.

Standard connections

ItemPriceIncludes
Sewer line, ADU to home's line$65 / LFTrench, 4" pipe, bedding, backfill, compaction
Sewer tie-in + cleanout$1,200 eachConnection to your home's line, required cleanout
Water line, in shared sewer trench$20 / LFPipe and fittings in the same trench as sewer
Water line, separate trench$35 / LFTrench, pipe, fittings, backfill
Water tie-in + ADU shutoff valve$750Tee after your City meter, dedicated ADU shutoff
Electric trench + conduit$40 / LFTrench and conduit per SRP/APS design
New meter service + ADU panel$6,000Meter base, main disconnect, ADU panel, grounding
ADU address (required for every Tempe ADU)$350SOKO request and coordination with the City
Utility and City feesAt costSRP/APS and City of Tempe, including the water development fee, passed through with no markup

Add-ons and site conditions

ItemPriceWhen it applies
Water submeter on ADU line$750Optional, for rental billing
Power from home's panel instead of new meter$3,500 + $40 / LFOptional, if load calc allows; replaces the $6,000 meter service (address is still required)
Sewer camera inspection$350Older homes or unknown pipe condition; common in Tempe
Sewer pump (ejector)$4,500 allowanceOnly if the ADU sits too low for gravity flow
Water meter upsizeCity fees at cost + $1,500Only if the fixture calculation exceeds your current meter
Caliche, rock, or hardscape removalCost + 25%Found during excavation

Example: a 40-foot run with shared sewer and water trench, a separate 40-foot electric trench, a new meter and the required address comes to about $13,300 before City and utility fees.

What moves the number

What this pricing assumes

We run this for you

In Tempe the job is knowing what's under an older lot before you price it, then handling the address, the development fee, and the SRP or APS application so none of it lands on you mid-build. Building a casita in Tempe? Check your property or call 480-660-3133.

Sources: Tempe Zoning and Development Code Section 3-402; Tempe City Code Chapters 27 and 33 and Appendix A fee schedule; City of Tempe ADU page and FAQ; SRP Electric Service Specifications; Maricopa County Onsite Wastewater Guide for Homeowners. City policies, utility requirements, and fees change; verify current requirements with the City of Tempe and your utility before making design decisions. Pricing shown is SOKO's standard connection pricing as of September 2026 and is confirmed in your written proposal.

Tempe ADU utilitiesTempe ADU addressTempe ADU development feeADU sewer connection TempeSRP ADU metercasita utility cost

Want the utility numbers for your lot?

Send us your address. We measure the runs, check the city rules, and put real connection pricing in your proposal — before anything gets drawn.