Permitting & Approvals

How Your ADU Connects to Sewer, Water & Electric in Phoenix (and What It Costs)

Detached casita in a Phoenix backyard

Every casita needs three things before anyone can live in it: somewhere for the water to come from, somewhere for it to go, and power. In the City of Phoenix, the rules for all three are unusually clear, and they happen to be the money-saving version. Here is exactly how your ADU gets connected, what we verify on your lot, and what each piece costs.

The short version

In Phoenix, your ADU shares the sewer and water service your home already has, and gets its own electric meter. That keeps connection costs down and gives the unit its own power bill from day one.

Sewer
Tie into your home's existing sewer line. Required by the City of Phoenix. No new street tap.
Water
Tie into your home's water line, after the meter. The City allows one water meter per lot for an ADU project.
Electric
New, separate SRP or APS meter for the ADU. Separate bill, no load added to your home's panel.

We keep every trench run as short as the site allows. Distance from your home's lines to the ADU is the single biggest driver of utility cost, which is why utility routing is part of where we place the unit, not an afterthought.

Sewer: one line, one account

Your ADU connects to your home's existing sewer line, not to a new city tap. Phoenix Water Services policy requires ADUs to share the home's sewer service, and the shared connection is still billed as one single-family account. That is spelled out in the City's ADU water and wastewater policy. A separate tap is only entertained through a technical appeal when sharing genuinely isn't feasible, and on a normal residential lot it almost always is.

What we verify at the site visit:

Water: tee off after your meter

Your ADU tees off your home's water line after the existing city meter, with its own shutoff valve. Phoenix allows one water meter connection per lot for an ADU project, so a second city meter from the street is not the standard path (see the City of Phoenix ADU process).

Electric: its own meter, its own bill

Your ADU gets its own electric meter from SRP or APS, whichever serves your home. That means a separate power bill and no added load on your home's panel.

Standard: new, separate meter

Option: power from your home's panel

We can instead feed the ADU from your home's electrical panel, with one shared bill. This works when a load calculation shows your panel has room, usually a 200-amp service. It's often a fit for family or guest use, and if you have rooftop solar it's usually the better economics. If your panel is too small, a new ADU meter is usually better value than upgrading your home's service.

What it costs in Phoenix

Utility connections are priced per linear foot of trench plus fixed connection items. Your proposal shows the measured run lengths for your site.

Standard connections

ItemPriceIncludes
Sewer line, ADU to home's line$65 / LFTrench, 4" pipe, bedding, backfill, compaction
Sewer tie-in + cleanout$1,200 eachConnection to your home's line, required cleanout
Water line, in shared sewer trench$20 / LFPipe and fittings in the same trench as sewer
Water line, separate trench$35 / LFTrench, pipe, fittings, backfill
Water tie-in + ADU shutoff valve$750Tee after your city meter, dedicated ADU shutoff
Electric trench + conduit$40 / LFTrench and conduit per SRP/APS design
New meter service + ADU panel$6,000Meter base, main disconnect, ADU panel, grounding
Second address (required for new meter)$350SOKO request and coordination with the City
Utility and City feesAt costSRP/APS, City of Phoenix, passed through with no markup

Add-ons and site conditions

ItemPriceWhen it applies
Water submeter on ADU line$750Optional, for rental billing
Power from home's panel instead of new meter$3,500 + $40 / LFOptional, if load calc allows; replaces the $6,000 meter service and $350 address
Sewer camera inspection$350Older homes or unknown pipe condition
Sewer pump (ejector)$4,500 allowanceOnly if the ADU sits too low for gravity flow
Water meter upsizeCity fee at cost + $1,500Only if the fixture calculation exceeds your current meter
Caliche, rock, or hardscape removalCost + 25%Found during excavation

Example: a 40-foot run with shared sewer and water trench, a separate 40-foot electric trench, and a new meter comes to about $13,300 before City and utility fees.

What moves the number

What this pricing assumes

We run this for you

Utility routing is decided on the first site visit, not discovered at plan review. We measure the runs, confirm your sewer and meter, apply to SRP or APS, and pull the second address, so the connection line in your proposal is a real number instead of an allowance. Building an ADU in Phoenix? Check your property or call 480-660-3133.

Sources: City of Phoenix Water and Wastewater Service Policies for ADUs; City of Phoenix ADU Residential Process; City of Phoenix Water Meter Sizing Guideline; SRP Electric Service Specifications. City policies, utility requirements, and fees change; verify current requirements with the City of Phoenix and your utility before making design decisions. Pricing shown is SOKO's standard connection pricing as of September 2026 and is confirmed in your written proposal.

Phoenix ADU utilitiesADU sewer connection PhoenixADU water meter PhoenixSRP ADU meterAPS ADU metercasita utility costADU trenching cost

Want the utility numbers for your lot?

Send us your address. We measure the runs, check the city rules, and put real connection pricing in your proposal — before anything gets drawn.